How Much Gravel for a 20x40 Driveway?

A 20 × 40 ft driveway with a 4 inch layer of gravel needs 9.88 cubic yards, which is about 13.8 tons. Order roughly 10% more to allow for compaction.

Change any number below to match your project. The gravel calculator works for any size.

Area shape

Enter your measurements to see the result.

How it's worked out

  1. Volume: 20 × 40 × 4 in ÷ 12 = 266.7 cu ft
  2. Cubic yards: 266.7 ÷ 27 = 9.88 yd³
  3. Tons: 9.88 × 1.4 tons per yard = 13.8 tons

20x40 driveway at other depths

DepthCubic yardsTons (approx.)With 10% extra
2 in4.946.97.6
4 in9.8813.815.2
6 in14.8120.722.8

A new driveway is usually built in layers: 4 to 6 inches of large crushed stone for the base, then 2 to 3 inches of smaller top stone. Refreshing an existing driveway takes about 2 inches. The 1.4 tons per yard figure is typical for gravel; ask your supplier for theirs.